Follow-up order for major LDPE compressor overhaul

December 3, 2019

The booster / primary compressor (Ingersoll Rand) and the hyper compressor (Burckhardt Compression) have been in operation for over 40 years. Thanks to the detailed planning we were able to manage the scope, including a challeng­ing foundation repair during the turnaround, according to schedule.

To overhaul both compressors at the same time while repairing the foundation for the booster / primary was a challenge. With Burckhardt Compression we had a partner that was working hand in hand with us and who acted mostly proactive on unanticipated situations. We finished the job on schedule and kept the plant shutdown time to a minimum.

Sjors Slots, Maintenance Engineer of SABIC Europe

Customer challenges

  • Major overhaul of 40-year-old booster / primary and hyper compressor scheduled
  • Booster / primary compressor challenges: oil leakage, uncertain foundation condition, removal of the electric motor
  • Looking for one contractual partner for entire project scope
  • Shortest possible delivery time
  • Suspicion of asbestos in compressor and cooling water system

Technical data

ManufacturerNon-BurckhardtBurckhardt
TypeBooster / primary 4HHE-5Hyper F8
Power2’160 kW / 2’900 hp6’624 kW / 8’880 hp
Speed333 rpm167 rpm
GasEthyleneEthylene
Suction Pressure2.33 bara / 29,00 psia246 bara / 3’568 psia
Discharge pressure272 bara / 3’945 psia2’696 bara / 39’100 psia

Our solution

  • On-site inspection and revision of both compressors
  • Booster / primary compressor:
    • Complete compressor disassembly on-site and crankcase removal
    • Repair of 44-year-old foundation according to our procedures
    • Repair works (machining) in local service center
    • New lubrication piping made in-house
  • Hyper / secondary compressor:
    • Reconditioning and replacement of hyper compressor components
    • Overhaul of cylinder lubrication pump

Customer benefits

  • Zero safety incidents / accidents due to highest safety standards and own QHSE project manager
  • Overall responsibility with one contractual part, reduced coordination efforts
  • Job performed on time, despite unexpected challenges during execution
  • Minimized oil leakage on booster / primary compressor

Get in touch

Talk to our services specialists.

Contact us